17 Feb 2005
CS 3243 - Constraint Satisfaction
9
Example: Task Scheduling
T1 must be done during T3
T2 must be achieved before T1 starts
T2 must overlap with T3
T4 must start after T1 is complete
T1
T2
T3
T4